Chuvash power engineers efficiently handled the damages caused by force of nature

6 june 2018

img_9202.jpgOn the afternoon of June 5, 2018, several districts of Chuvashia were affected by the squall wind with gusts up to 23 m/s, rain and lightnings. Power outages occurred in a number of settlements in the Alatyr, Vurnar, Krasnie Chetai village, Urmarsk, Yalchik, and Komsomol districts of the republic.

The power engineers of Chuvashenergo, a branch of IDGC of Volga, PJSC (a member of the Rosseti group) immediately started recovery activities. To repair the damage, 39 teams were mobilized, which is 123 people, as well as 42 special equipment units. Thanks to the professionalism and efficiency of the company's specialists, it was possible to fully restore the power supply by the evening.